After protracted litigation challenging plans to build 130 wind turbines, each 440 feet tall, in a 25 square mile area of Nantucket Sound, the D.C. Circuit last month denied petitions for review of the Federal Aviation Administration’s (“FAA”) determination that the turbines would pose no hazard to air navigation.

The petitioners, the Town of Barnstable, Massachusetts and a non-profit group of pilots and others, challenged the no hazard determinations based on the FAA’s failure to analyze the safety risks posed by the project and to perform an environmental review required by the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4332.  The D.C. Circuit had previously vacated a 2010 no hazard determination based on the FAA’s failure to consider potential adverse effects of the turbines on pilots operating under visual flight rules (“VFR”) and the potential that electromagnetic radiation from the turbines would interfere with radar systems in nearby air navigation facilities.

Noting the circumstances had changed after the FAA upgraded the radar and beacon at Otis Airfield, the circuit court’s January 22, 2014 opinion upheld the FAA’s 2012 no hazard determinations.  The court concluded that the FAA properly based its determinations on aeronautical studies conducted according to the FAA Handbook, Procedures for Handling Airspace Matters, FAA Order JO 7400.2J (February 9, 2012), of which Section 3 on identifying and evaluating aeronautical effect was applicable.  According to the court, the FAA could reasonably view its Handbook procedures implementing the Secretary of Transportation’s regulations as requiring a threshold finding before triggering the need for a more advanced “adverse effects” analysis under Handbook Section 6–3–3 which states that “[a] structure is considered to have an adverse effect if it first … is found to have physical or electromagnetic radiation effect on the operation of air navigation facilities.”
 Continue Reading D.C. Circuit Upholds FAA’s “No Hazard” Determinations Regarding Electromagnetic Radiation from Nantucket Sound Wind Turbines

Recent appellate cases have once again brought to the fore the critical importance of the “exhaustion of administrative remedies” for any potential challenger to an agency action based on noncompliance with the California Environmental Quality Act (“CEQA”), the National Environmental Policy Act (“NEPA”) and other laws meant to protect the environment and public.

In California, as example, public projects such as road construction, airport development, and power facilities, as well as private projects such as shopping centers are challenged on the basis of the failure to exhaust administrative remedies, or to present the alleged grounds of noncompliance “to the public agency orally or in writing . . . during the public comment period provided by this division or prior to the close of the public hearing . . .” Cal. Pub. Res. Code § 21177.

All too often, individuals, environmental organizations and public agencies wait to make their decisions to challenge the analysis of a project’s environmental impacts until their frustration peaks, and the time for filing a legal challenge arrives. [The usual time for filing a CEQA challenge is very short – 30 days from the filing by the agency of its Notice of Determination (“NOD”) which marks the final agency action in the CEQA process. NEPA is normally 60 days from the signing of the Record of Decision (“ROD”).] By that time, however, it is too late, because “exhaustion of administrative remedies is a jurisdictional prerequisite to maintenance of a CEQA action.” Bakersfield Citizens for Local Control v. City of Bakersfield, 124 Cal.App.4th 1184, 1199 (2004).
 Continue Reading Don’t Procrastinate: Make Your Comments on Environmental Analyses Early and Often