In a surprising decision, Surface Transportation Board Decision, Docket No. FD35861, December 12, 2014 (“Docket”), the Federal Surface Transportation Board (“Board”) ruled that the application of the California Environmental Quality Act (“CEQA”), Cal. Pub. Res. Code § 21000, et seq., to the 114 mile high-speed passenger rail line between Fresno and Bakersfield, California is preempted in its entirety by federal law.  The Board’s decision is not only surprising in the context of prevailing legal authority, but also potentially important in the context of other modes of transportation.  

The decision is surprising because it went far beyond the scope of the petition filed by the responsible State agency, the California High-Speed Rail Authority (“Authority”).  The Authority asked only that the Board find that injunctive relief as a remedy under CEQA is foreclosed as preempted by the Interstate Commerce Commission Termination Act (“ICCTA”), Pub.L. 104–88, 104th Congress, and is, thus, barred under 49 U.S.C. § 10501(b) which gives the Board jurisdiction over “the construction, acquisition, operation, abandonment, or discontinuance of spur, industrial, team, switching, or side tracks, or facilities, even if the tracks are located, or intended to be located, entirely in one State,” 49 U.S.C. § 10501(b)(2).  The Authority further argued that, as it had completed CEQA review in May 2014, the Board need not address whether CEQA is generally preempted, but need only address whether injunctive relief resulting in a work stoppage is available as a remedy in the lawsuits filed against the Authority.
 
Despite the Authority’s limited petition, the Board expanded its ruling to include a finding that § 10501(b) prevents the states and localities from intruding into matters that are “directly regulated by the Board (e.g., rail carrier rates, services, construction, and abandonment),” Docket, p. 8, and from “imposing requirements that, by their nature, could be used to deny a rail carrier’s ability to conduct rail operations.”  Id.  The Board employs the rationale that “Section 10501(b) [ ] is intended to prevent a patchwork of local regulation from unreasonably interfering with interstate commerce.”  Id.  
 
The Board recognizes, however, that “[n]ot all state and local regulations that affect rail carriers are preempted by § 10501(b).”  Id. at p. 9.  It acknowledges further that “State and local regulation is appropriate where it does not interfere with rail operations,” Id., and that “[l]ocalities retain their reserved police powers to protect the public health and safety so long as their actions do not unreasonably burden interstate commerce.”  Id.  
 
On that basis, and ignoring that “states and towns may exercise their traditional police powers . . . to the extent that the regulations ‘protect public health and safety, are settled and defined, can be obeyed with reasonable certainty, entail no extended or open-ended delays, and can be approved (or rejected) without the exercise of discretion on subjective questions,’” Id. citing Green Mountain v. Vermont, 404 F.3d 638, 643 (2nd Cir. 2005), the Board concluded that CEQA was categorically preempted as a “state preclearance requirement that, by its very nature, could be used to deny or significantly delay an entity’s right to construct a line that the Board has specifically authorized, thus impinging upon the Board’s exclusive jurisdiction over rail transportation,” Docket, p. 10, citing DesertXpress Enters., LLC-Pet. For Declaratory Order, slip op. at 5.  The Board further found that CEQA lawsuits “can regulate rail transportation just as effectively as a state statute or regulation.”  Id. at 14, citing, inter alia, Maynard v. CSX Transp., Inc., 360 F. Supp. 2d 836, 840 (E.D. Ky. 2004) [explaining that common law suits constitute regulations].  
 
The Board decision, however, appears to be based on two fundamental misconceptions. 
 

Continue Reading The Federal Surface Transportation Board Finds California Environmental Quality Act Preempted as Applied to High-Speed Rail Projects