In a surprising climax to the long controversy concerning helicopter flights and attendant noise impacts on the North Shore communities of New York’s Suffolk County, the FAA, on July 6, issued a “Final Rule,” making mandatory the current voluntary flight path for helicopters one mile offshore, but allowing the “Final Rule” to sunset on August 6, 2014, two years from the effective date, “unless the FAA determines a permanent rule is merited.”  The route commences 20 miles northeast of LaGuardia, near Huntington, New York, and remains approximately one mile offshore until reaching Orient Point, near the eastern end of Long Island, with deviations allowed for safety reasons, and to allow helicopters to transit over land to reach their ultimate destinations. 

The FAA discloses that its decision to promulgate the original voluntary rule arose from the numerous complaints of noise from helicopter overflights brought to its attention by Senator Charles Schumer of New York and Representative Tim Bishop of Long Island’s North Shore in October, 2007.  The subsequent mandatory rule apparently resulted from continued political pressure by residents who are “unbearably and negatively” impacted, particularly during the summer months when the number of helicopters, as well as deviations from the voluntary routing, seem to increase dramatically.  The real surprises in the “Final Rule,” however, are FAA’s rationale for: (1) making the route mandatory, a rationale which seems to apply equally to currently voluntarily procedures at other airports; and (2) the Rule’s sunset provision. 
 Continue Reading FAA Issues Temporary “Final Rule” for the New York North Shore Helicopter Route

On June 18, 2012, the Environmental Protection Agency (“EPA”) posted in the Federal Register, Vol. 77, No. 117, 36342, its Final Rule adopting several new aircraft engine emission standards for oxides of nitrogen (“NOx”) for aircraft turbofan or turbojet engines with rated thrusts greater than 26.7 kilonewtons (kN), or in common parlance, commercial passenger and freighter aircraft normally used at airports across the United States.  The rule applies only to the manufacture of new aircraft engines, not to retrofit of existing aircraft engines. 

The EPA’s stated purpose in enacting the new rule is two-fold.  First, NOx is strongly correlated with nitrogen dioxide (“NO2”) which is a “criteria pollutant” under the EPA’s National Ambient Air Quality Standards (“NAAQS”), and is an important precursor gas in the formation of ozone and secondary particulate matter (“PM2.5”) which are common air pollutants in urban areas where airports are often located.  Second, the new rule will bring United States’ emissions standards into consistency with those established by the International Civil Aviation Organization (“ICAO”), see ICAO Annex 16, Vol. II, 2010 that the U.S. helped to develop and supports as part of the international process. 

The rule contains six major provisions.
 Continue Reading EPA Adopts Final Rule Further Restricting NOx Emissions from New Aircraft Engines

On March 27, 2012, the Environmental Protection Agency (“EPA”) proposed a Carbon Pollution Standard for New Power Plants (“Carbon Standard”), setting national limits on the amount of carbon pollution power plants built in the future can emit.  The rules are a reaction to the United States Supreme Court’s decision in Massachusetts v. EPA, 549 U.S. 497 (2007), in which, among other things, the Supreme Court held that greenhouse gases, including carbon dioxide (“CO2”) are air pollutants under the Clean Air Act.  EPA was charged by the court with issuing an “endangerment finding,” i.e., a determination that greenhouse gases threaten public health and welfare which was issued on December 15, 2009. 

Immediately upon their initial promulgation, the Carbon Standard generated more contention than power plants generate greenhouse gases.  The Wall Street Journal charged, in an article entitled “Killing Coal,” that “because the putative ‘regulatory impact’ would be zero, there are also no benefits.”  It went on to say that, because the rule would apply not only to new plants but also to every plant upgrade or modification in existing facilities; and because the technology required to meet the standard is still speculative, the EPA’s real goal must be to put a stop to the use of coal in electricity generating. 

The EPA immediately fired back, characterizing the critique of the Carbon Standard in, among others, the Wall Street Journal, as examples of “fact free assault.”  Assistant Administrator Gina McCarthy pointed to the “example” that, in fact, “this standard only applies to new sources – that is power plants that will be constructed in the future.  This standard would never apply to existing power plants.”  Moreover, again pointing to the Wall Street Journal editorial, she stated “the proposed rule explicitly does not apply to facilities making such modifications.  In fact, EPA did not propose a standard for any modifications.”

The proposed Carbon Standard speaks for itself. Continue Reading EPA’s Proposed Carbon Pollution Standard for New Power Plants Creates Controversy

On March 28, 2012, the Environmental Protection Agency (“EPA”) and Department of Justice (“DOJ”) announced their first settlement of an enforcement action addressing Federal Clean Air Act (“CAA”) violations in the marine engine manufacturing and ship building industries.  Under that settlement, Coltec Industries, Inc. (“Coltec”) and National Steel and Shipbuilding Company (“National Steel”) have agreed to pay a civil penalty of $280,000 and spend approximately $500,000 on an environmental project to resolve alleged violations of the CAA and the EPA’s marine diesel engine air rules.  Coltec is a subsidiary of EnPro Industries, Inc. and operates Fairbank Morse Engines which supplies marine propulsion and ship service systems to the United States Navy and Coast Guard.  National Steel is a subsidiary of General Dynamics which designs and builds support ships, oil tankers and dry cargo carriers for the United States Navy and commercial markets.Continue Reading EPA Takes Its First Enforcement Action Under Marine Diesel Engine Air Rules

Challengers to the determinations of Federal agencies do not go to court on a level playing field with their governmental adversaries.  Federal courts have long taken the position that deference is properly accorded to an agency making decisions within its area of technical expertise.  That position may now be changing, at least with respect to two specific sets of legal circumstances. Continue Reading Federal Court Finds that Judicial Deference Does Not Mean “Do Everything Federal Entity Requests”

On Thursday, March 16, 2012, the Environmental Protection Agency (“EPA”) took the almost unprecedented step of publishing in the Federal Register a correction to its prior definition of “regulated new source review pollutant” (“Rule”) contained in two sets of Prevention of Significant Deterioration (“PSD”) regulations, 40 C.F.R. §§ 51.166 and 52.21, and in EPA’s Emissions Offset Interpretative Ruling, 40 C.F.R. Part 51, Appendix S, 77 Fed.Reg. 15,656. The purpose of the revision is to correct an “inadvertent error” dating back to the Rule’s promulgation in 2008 when the then-existing definition was changed to require that particulate matter emissions, both PM10 and PM2.5, representing three separate size ranges of particulates, must include “gaseous emissions, source or activity which condense to form particulate matter at ambient temperatures,” i.e., condensable particulate matter.  See, e.g., 40 C.F.R. § 51.166(b)(49)(vi).  Previously, EPA’s regulations only required the filterable fraction, not the condensable particulate matter, to be considered for new source review purposes.  The 2008 change therefore imposed an unintended new requirement on State and local agencies and the regulated community.Continue Reading EPA Issues “Amendment” to Definition of Condensable Particulate Matter as Regulated New Source Review Pollutant

On Tuesday, March 6, 2012, Tinicum Township, Pennsylvania and its partners County of Delaware, Pennsylvania; Thomas J. Giancristoforo; and David McCann (“Petitioners”) took their grievances with the ongoing expansion project at Philadelphia International Airport (“PHL”) to the 3rd Circuit Federal Court of Appeals in Philadelphia.  Petitioners, made up of communities and residents surrounding the airport

As we reported yesterday in our blog titled “FAA Reauthorization Act Exempts Next Generation Airspace Redesign Projects from Environmental Review,” Congress is set to act on the conference version of H.R. 658 (“Act”), a Bill the nominal purpose of which is to fund the Federal Aviation Administration (“FAA”) for 2011-2014, a task Congress has been unable or unwilling to accomplish for the last two years. 

The legislation goes far beyond funding, however.  Toward another stated purpose – to “streamline programs” – the Act sets out the parameters for establishment and operation of FAA’s Next Generation Transportation System (“NextGen”).  Not stopping there, it also “creates efficiencies” by exempting the NextGen program from environmental review under the National Environmental Policy Act, 42 U.S.C. § 4321, et seq. (“NEPA”), Act, § 213.  Thus, whole communities around at least 30 “core” airports might be newly impacted by aircraft overflights seemingly without the opportunity for public review and comment before the NextGen project is implemented, and without an avenue of leverage in the courts afterwards.  All is not yet lost, however.
 Continue Reading There May Still Be Time to Weigh in on the Congressional Action to Exempt the NextGen Technologies from NEPA Review

In a monument to political deal making, the United States Congress is today considering, in the House and Senate Aviation Committees, the "FAA Modernization and Reform Act of 2012," H.R. 658 ("Act") to, among other things, "authorize appropriations to the Federal Aviation Administration for fiscal years 2011-2014 . . ." It is, however, the other provisions of the legislation which most profoundly affect the public.   

Purportedly to "streamline programs, create efficiencies, reduce waste and improve safety and capacity," the most recent version of the Act to emerge from the House-Senate Conference Committee exempts all new area navigation ("RNAV") and required navigation performance ("RNP") procedures, which collectively comprise the "Next Generation Air Transportation System" ("NextGen"), Act § 201, Definitions, from environmental review under the National Environmental Policy Act, 42 U.S.C. § 4321, et seq. ("NEPA"). 

The Act, generally, mandates that all "navigation performance and area navigation procedures developed, certified, published or implemented under this section [Section 213] shall be presumed to be covered by a categorical exclusion (as defined in § 1508.4 of Title 40, C.F.R.) under Chapter 3 of FAA Order 1050.1E, unless the Administrator determines that extraordinary circumstances exist with respect to the procedure." Act, § 213(c)(1).   

The Act expands on this mandate in § (c)(2). "NEXTGEN PROCEDURES – Any navigation performance or other performance based navigation procedure developed, certified, published or implemented that, in the determination of the Administrator, would result in measurable reductions in fuel consumption, carbon dioxide emissions, and noise, on a per flight basis, as compared to aircraft operations that follow existing instrument flight rule procedures in the same airspace, shall be presumed to have no significant effect on the quality of the human environment and the Administrator shall issue and file a categorical exclusion for the new procedure."Continue Reading FAA Reauthorization Act Exempts Next Generation Airspace Redesign Projects from Environmental Review

Following in the footsteps of his colleagues, on January 6, 2012, Assemblyman Mike Feuer introduced legislation that would give rail projects the same type of relief from California Environmental Quality Act (“CEQA”) requirements that were received in the last session by the proposed NFL stadium in Los Angeles, and some renewable energy projects. Notably, the CEQA amendments enacted for the NFL stadium include a very short time frame of 175 days for resolution of CEQA issues. While current CEQA litigation may extend to two years or more, depending on the complexity of the project and workload of the court, it stands to reason that issues surrounding local projects such as the stadium, with local traffic, noise and air quality impacts, may potentially be resolved within the 175 day timeframe. Rail projects are of far different scope, geographic extent, and are subject to a different set of laws.Continue Reading Legislature Asked to Grant CEQA Relief for Rail Projects